Scoping/

Great Rail Journeys

Feasible
241–439 man-days
Present
1

Customer Context

Business Context

PE-owned (Vitruvian Partners), mandated to triple FIT revenue in 3-5 years. Current system (Softrip) has 7-10 day booking confirmations, "bank statement" quality quotes killing conversion. 7 US agents at 30% conversion — better docs = better conversion = growth justification. This is GRJ's 3rd platform replacement attempt in 10 years — must be the last. FIT is only 30-40% of the business; escorted tours are the majority.

Current Systems: SoftTrip (FIT booking/reservations — "significant barrier to growth"), Extrali by Koderly (escorted tours — no desire to migrate short-term), Sage (accounting/ERP — source of truth for "closing the book"), Braintree (VBR/US payments), APEXX (GRJ/UK payments — complex, multi-acquirer), PayPal PayFlow (US legacy, sits on Braintree), Power BI (enterprise analytics), Lloyds banking system (supplier payments via CSV)
Revenue: FIT revenue — UK: GBP 5M (luxury rail, mainly Belmond). US (VBR): USD 25M. Total FIT: ~GBP 30M. Group turnover: GBP 175M total (web-sourced, requires confirmation — up from GBP 88M in 2018). FIT is ~30-40% of total. Growth targets: US to USD 65M, UK to GBP 10M. Aspiration: GBP 90M total. Users: ~40-45 starting (Tracy, Feb 12 — to be confirmed), ramping to 51. ~7,000 booked PAX/year (note: booked not departed — pricing recalculation needed). 50,000+ customers/year total group (web-sourced). Implementation CAPEX: EUR 400-500k confirmed as "absolutely fine" (Feb 12). ARR/licensing is the real sign-off hurdle for Vitruvian — ~EUR 236k/year accepted.
Deal Status: Preferred vendor — GRJ taking only Kaptio to Vitruvian for approval. MSA being drafted. Contract target: early March 2026. CEO demo/pitch with Dave completed. Steering group approved.

Timeline

Target: 31 July 2026 (customer desired — avoiding 2027 bookings in SoftTrip)
Rationale: They don't want to start selling 2028 product on SoftTrip. Dec 2026 is when they'll start sending out documentation. CEO-driven growth urgency under PE ownership. SoftTrip 3-year contract — notice by October 2026, full exit by February 2027.
Realistic: October 2026 for full FIT scope (both brands). July 2026 achievable only with stripped scope — 3 outcomes deferred, Braintree-only payments, essential documents only. See Scenario A vs B.
Kerry accepts phased approach if value is clear. Tracy says "there's a bit of wriggle room" (Feb 12). They don't want to OPERATE 2027 on SoftTrip — but Dec 2026 doc-sending is the real deadline, not Jul go-live.

Team

sales: 7
operations: Unknown
technical: 3
management: 4

Competitive Context

Competitors: Nezasa (resolved — Kaptio selected as preferred vendor, Feb 2026)

Nezasa strong on front office, weaker on mid/back office and escorted tour path. Kaptio won on: complete system (front+mid+back office), Edge Docs/Pay quality, Salesforce CRM, and path from FIT to escorted tours. Decision made after all-day workshops with both vendors.

Assumptions

  • Phase 1 scope is limited to existing Kaptio capabilities — no new product development
  • Supplier connectivity at go-live limited to GP Solutions available suppliers (Jonview, Discover Holidays)
  • Rail booking is manual/static at go-live — live rail API integration is Phase 2+ or co-investment
  • GRJ provides dedicated project resources for workshops and UAT (Kerry flagged as a need)
  • No data migration — fresh Kaptio org. Forward-traveling bookings (post Feb 1 2027) manually transferred
  • No Salesforce org exists — clean org provisioning
  • Kerry Jenkin (CIO) has authority to make scope decisions; Dave (CEO) approves Vitruvian presentation
  • Phased delivery is acceptable — not all features at go-live
  • Edge Docs is the primary document generation approach (not legacy Kaptio VF docs)
  • SoftTrip notice by October 2026, full exit by February 2027
  • Service code mapping tooling provided by Kaptio during implementation (CTO direction, Feb 12)
  • Kaptio resourcing must account for Tauck and DuVine go-lives in March/April 2026
  • No data migration — fresh Kaptio org, manual move of forward-traveling bookings (CTO direction, Feb 12)
  • No online bookings at MVP — post go-live scope (confirmed Feb 12)
  • Kaptio does all heavy lifting — GRJ IT team is 3-4 people with no Salesforce expertise
  • Escorted tour scoping explicitly excluded from this engagement
  • CAPEX (EUR 400-500k) confirmed as fine — ARR/licensing is the real Vitruvian sign-off hurdle
  • APEXX integration follows KTPay two-stage discovery + development process
  • Customizations via The Edge framework to protect core upgradeability
  • Kaptio = native Salesforce app + GCP backend; real-time sync via streaming API
  • Salesforce standard reports + dashboards sufficient for go-live. 1-2 days reporting training included in Phase 3
  • Parallel operation period: ~4 months (Oct 2026 - Feb 2027). New bookings in Kaptio, in-flight SoftTrip bookings wind down
  • ~100k customer records assumed — no migration, fresh Kaptio org
  • Website integration is a separate project post-MVP go-live — not scoped in this engagement
2

How We Work

Kaptio's implementation approach and the roles & responsibilities split.

🎯

Approach

Outcome-based phased delivery

🔍

Discovery Process

Structured discovery workshops (2-3 per week over 4-7 weeks) led by Kaptio implementation consultants. Each workshop focuses on a specific outcome area: foundation, product setup, pricing, channel configuration. GRJ provides subject-matter experts (Kerry, Julian, Missy) — Kaptio drives the agenda and captures all requirements. Discovery outputs: configured prototype environment, validated data model, and detailed delivery plan.

🚀

Delivery Model

Kaptio-led implementation with iterative build-validate cycles. Each phase delivers a working increment that the customer can review and test. Configuration, data loading, and integration work is done by Kaptio. UAT is structured with test scripts and guided walkthroughs. Training is hands-on in the live environment — no separate training instance. Hypercare (3 weeks post go-live) provides dedicated support channel.

📋

Governance

Bi-weekly steering committee (Kerry + Kaptio project lead) for decisions and escalation. Weekly status updates via shared dashboard. Dedicated Slack/Teams channel for day-to-day communication. Formal milestone sign-offs at phase boundaries. Change requests processed through defined scope change process — assessed for timeline and cost impact before approval.

Roles & Responsibilities

Who does what — Responsible, Accountable, Consulted, Informed

ActivityKaptioCustomerNotes
Discovery workshopsRCKaptio leads and drives all workshops. GRJ provides SMEs (Kerry, Julian, Missy) for validation.
Platform configurationRIKaptio configures Salesforce org, business units, currencies, user setup, security.
Data model & service catalog setupRCKaptio builds catalog structure. GRJ validates package data and pricing rules.
Service code mapping (Jonview/Discover)CRGRJ maps their product codes to supplier codes. Kaptio provides tooling and guidance.
Supplier API integration (GP Solutions)RIKaptio handles all technical integration work.
Payment gateway setup (Braintree + APEXX)RCKaptio configures KTPay. GRJ provides merchant credentials and gateway access.
Edge Docs template designRAKaptio designs and builds document templates. GRJ approves branding and content.
Email template configurationRAKaptio configures email flows. GRJ approves messaging and branding.
UAT test executionCRGRJ executes test scripts in live environment. Kaptio provides scripts, guidance, and issue triage.
User trainingRAKaptio delivers hands-on training. GRJ ensures team attendance and adoption.
Salesforce reporting trainingRA1-2 days training on standard Salesforce reports and dashboards. GRJ identifies reporting champions.
Go-live cutoverRAKaptio manages cutover checklist. GRJ approves go/no-go decision.
Hypercare support (3 weeks)RCDedicated Kaptio support channel. GRJ escalates issues through defined process.
Forward-booking manual transferCRGRJ manually moves post-Feb-2027 bookings from SoftTrip to Kaptio. Kaptio provides process guidance.
Sage export format definitionCRGRJ defines required Sage flat file format. Kaptio assesses feasibility and builds export.
Change management & adoptionCRGRJ drives internal change management. Kaptio provides materials and best practices.
3

What We Know

Discovery progress and unanswered questions that affect estimation confidence.

Discovery Progress

92% Complete
24
Confirmed
0
Assumed
2
Unknown
26
Total

2 Unanswered Questions — Blocking Estimation Confidence

How does your team typically adapt to new systems? Do you have internal champions who can drive adoption?Change management risk assessment
How many bookings do you process per month/year? What is the seasonal pattern?Volume context for system sizing and go-live timing
4

Two Paths Forward

Each scenario represents a different balance of scope, timeline, and risk.

Select a path to see the detailed implementation plan below.

Detailed implementation plan for the selected scenario below
Showing: Realistic FIT Launch
5

What We'll Deliver

13 outcomes across 4 phases.

6

How We'll Get There

Implementation phases and timeline feasibility.

Implementation Phases

4 phases

Phase 1: Foundation & Core Configuration

Platform setup, org structure, suppliers, catalog, pricing, customers, security — includes discovery workshops

8-10 weeks
2026-032026-05
360° Guest IntelligenceEnterprise-Grade SecurityPricing Power at Your FingertipsSupplier Network, SimplifiedSupplier Partnerships, StrengthenedYour Kaptio Foundation

Proper discovery pace. Sage integration design included. Pricing workshop.

Phase 2: Product & Booking Workflows

FIT package building, quoting, reservations, selling, booking management — pilot build with GRJ data

8-10 weeks
2026-062026-08
Confirm Bookings, EffortlesslyOperate Bookings Day-to-DayQuote Trips That Convert

Pilot build with representative GRJ data for both brands.

Phase 3: Channel, UAT & Go-Live

Payments (Braintree + APEXX), documents, email comms, passenger info, UAT, training, go-live, hypercare

8-10 weeks
2026-082026-10
Automated Guest CommunicationsDocuments, Delivered AutomaticallyGuest Details, Captured SeamlesslyPayments That Just Work

Both brands go-live. APEXX + Braintree. Full document suite. 3-week hypercare.

Phase 4: Post Go-Live Enhancements

Website integration, self-service, reporting, extended integrations, Sage export refinement

8-12 weeks
2026-112027-01
Bookings, From Quote to CompleteBusiness Intelligence at Your FingertipsFinancial Clarity, FastGuest Self-Service, 24/7System Integrations Made SimpleYour Website, Booking-Ready

Scope and timing TBD based on FIT go-live success.

Can We Do This in Time?

Feasible
Contract Sign
2026-03-01
Target Go-Live
2026-10-31
Working Days
170
Delivery FTE
4.5
Effective Capacity
585 man-days
Capacity vs. Estimate
585d capacity
238438d estimate
Buffer:+147 man-days(34% of high estimate)
Resource Contention
3 FTE (instead of 4.5) for first 6 weeks — Tauck and DuVine go-lives end of March / early April 2026
Constraints
  • APEXX integration scope still unknown — needs product/engineering assessment
  • Sage integration not fully scoped (finance export workflow)
  • Commission handling complexity (UK deducts at source, US pays gross)
  • Rail ticket voucher workflow needs product confirmation
  • Resource contention: 3 FTE (not 4.5) for first 6 weeks — Tauck and DuVine go-lives
7

System Transition

The SoftTrip → Kaptio cutover model — parallel operation, not parallel booking.

Option A: Clean Break

All new bookings in Kaptio from day one. SoftTrip operates in-flight only.

!

Key Principle: No Data Migration, Clean Cutover

Fresh Kaptio org. All new bookings in Kaptio from go-live. Only forward-traveling bookings (post Feb 1 2027) manually transferred. SoftTrip fully decommissioned by February 2027.

Key Milestones

Oct 2026
Kaptio Go-Live
All NEW bookings created in Kaptio from this date. SoftTrip notice given.
Oct–Jan
Parallel Operation
New bookings in Kaptio. In-flight SoftTrip bookings continue until travel date passes.
Jan 2027
Forward Booking Transfer
Any SoftTrip booking with travel date after Feb 1 2027 manually transferred to Kaptio.
Feb 2027
SoftTrip Decommissioned
Full SoftTrip end-of-life. All operations in Kaptio.

System Activity Over Time

Pre Go-Live
Mar–Sep 2026
Go-Live
Oct 2026
Parallel Operation
Nov 2026 – Jan 2027
Full Cutover
Feb 2027
Kaptio
Implementation, UAT, training
All NEW bookings
All new + transferred bookings
All operations
SoftTrip
All bookings & operations
Operate in-flight bookings only
In-flight until travel date passes
Decommissioned
New Bookings
SoftTrip
Kaptio
Kaptio
Kaptio

Advantages

  • +Clean break — agents only create bookings in one system from go-live
  • +Shorter parallel period (~4 months)
  • +No ambiguity about which system to use for a new booking
  • +Simpler training — agents only learn Kaptio for new work

Trade-offs

  • Higher go-live risk — all new bookings immediately depend on Kaptio
  • Manual transfer of forward-traveling bookings (post Feb 2027)
  • No gradual ramp — full commitment from day one
?

Scoping Session Discussion Point

Which transition model does GRJ prefer? Option A (clean break — all new bookings in Kaptio from day one) or Option B (gradual handover — travel-date cutoff with both systems taking new bookings)? Both approaches have been proven at other operators — Kaptio has delivered both models successfully.

8

Investment

Effort estimates, cost range, and per-phase breakdown.

Capacity Analysis

Feasible
Contract Sign
2026-03-01
Target Go-Live
2026-10-31
Working Days
170
Delivery FTE
4.5
Effective Capacity
585 man-days
Capacity vs. Estimate
585d capacity
238438d estimate
Buffer:+147 man-days(34% of high estimate)
Resource Contention
3 FTE (instead of 4.5) for first 6 weeks — Tauck and DuVine go-lives end of March / early April 2026
Constraints
  • APEXX integration scope still unknown — needs product/engineering assessment
  • Sage integration not fully scoped (finance export workflow)
  • Commission handling complexity (UK deducts at source, US pays gross)
  • Rail ticket voucher workflow needs product confirmation
  • Resource contention: 3 FTE (not 4.5) for first 6 weeks — Tauck and DuVine go-lives

Estimation Summary

Total Man-Days
241–439 man-days
Indicative Cost
€200,030–€364,370
Timeline Feasibility
Feasible
Team FTE
3

9 of 13 outcomes have full data; 4 have partial data; 0 need more content. Average maturity: 79/100.

To increase confidence:
  • Document pitfalls and risks
  • Create golden config for this outcome

Phase 1: Foundation & Core Configuration

Medium Confidence
Man-Days: 102–193 man-days
Duration: 6.8–12.9 weeks
Overhead: 17–32 man-days
Your Kaptio Foundation
×1.4512–22 man-days
Supplier Partnerships, Strengthened
×1.1513–23 man-days
Supplier Network, Simplified
×1.523–42 man-days
Pricing Power at Your Fingertips
×1.5223–43 man-days
360° Guest Intelligence
×1.18–17 man-days
Enterprise-Grade Security
×1.266–14 man-days

Phase 2: Product & Booking Workflows

Medium Confidence
Man-Days: 71–120 man-days
Duration: 4.7–8 weeks
Overhead: 12–20 man-days
Quote Trips That Convert
33–54 man-days
Confirm Bookings, Effortlessly
13–23 man-days
Operate Bookings Day-to-Day
13–23 man-days

Phase 3: Channel, UAT & Go-Live

High Confidence
Man-Days: 68–126 man-days
Duration: 4.5–8.4 weeks
Overhead: 11–21 man-days
Payments That Just Work
×1.5220–35 man-days
Documents, Delivered Automatically
×1.3823–41 man-days
Automated Guest Communications
7–16 man-days
Guest Details, Captured Seamlessly
7–13 man-days
9

Risks & Next Steps

Known risks and open questions that need answers before finalizing.

Risks (11)

APEXX payment gateway is NOT currently supported by Kaptio — UK payments blocked until integration

Mitigation: Scope APEXX integration effort with product/engineering. Consider Braintree for both brands at MVP (US first). APEXX may require custom connector development.

HIGH

July 2026 go-live requires stripped scope — 3 outcomes deferred, Braintree only, essential documents only. Buffer is razor-thin (5 man-days).

Mitigation: Two scenarios showing trade-offs. Scenario A (Jul) achievable only with significant scope deferral — operations, email, passenger info, APEXX all pushed to fast-follow. Tracy says "there's a bit of wriggle room" (Feb 12). Real deadline is Dec 2026 (start sending docs). Recommend October 2026 (Scenario B) for full scope.

HIGH

This is GRJ's 3rd platform replacement attempt in 10 years — failure risk and executive fatigue

Mitigation: Demonstrate clear progress early. Phased delivery with visible milestones. Reference Railbookers success (migrated from SoftTrip to Kaptio).

HIGH

CRM scope creep — Kerry wants Kaptio CRM across entire group (escorted + FIT), but FIT is only 30-40% of business

Mitigation: FIT-first agreed. Groups scoped separately. Architecture discussion (Jan 8) confirmed simultaneous CRM use is "uncommon but feasible." Keep FIT launch clean and separate.

HIGH

Supplier connectivity gap — only 2 of 22 suppliers covered by GP Solutions at go-live (Hotelbeds dropped)

Mitigation: Jonview + Discover cover ~95% of volume. Set clear expectations: 2 API suppliers at go-live, rest manual. Rail: Distribution (MGB aggregator) is 2027 prospect — Nazara currently integrating.

MEDIUM

Sage/ERP integration — finance team's #1 concern. Data volume bottleneck, period locking, export format.

Mitigation: Include Sage export design in Phase 1 discovery. Kerry agreed to work on ideal API structure. Not a Kaptio replacement for ERP.

MEDIUM

Kaptio resource contention — Tauck and DuVine go-lives end of March / early April 2026

Mitigation: Ring-fence GRJ resources. First 6 weeks may have reduced FTE availability (3 instead of 4.5). Absorbed by discovery phase.

MEDIUM

Booked vs departed PAX — pricing model needs recalculation

Mitigation: Tracy to recalculate with correct volume basis. Extra 1,000 PAX = GBP 11,250 additional cost.

MEDIUM

Quest product stability — TTC dependencies and capacity collision flagged

Mitigation: Monitor Quest roadmap. GRJ delivery benefits from TTC-funded enhancements in H1 2026.

MEDIUM

Manual forward-booking transfer — volume and effort of manually moving post-Feb-2027 bookings from SoftTrip

Mitigation: CTO directed no migration — fresh Kaptio org (Feb 12). Only forward-traveling bookings manually moved. Assess volume during Phase 1 discovery.

LOW

Customer resource capacity — GRJ expects Kaptio to do all heavy lifting with only 3-4 IT staff

Mitigation: Plan for Kaptio-led delivery. GRJ provides SMEs (Julian, Missy) for discovery and UAT but not implementation capacity. Build this into resourcing and pricing. No dedicated GRJ PM confirmed.

HIGH

Open Questions (9)

Sorted by priority — high priority questions have the biggest impact on estimation confidence.

What is the exact APEXX integration scope and effort? Is it a 2-week or 2-month effort?

high

APEXX is UK payment gateway. NOT currently supported. Needs product/engineering assessment before UK go-live timing can be confirmed. Tad noted it is complex (multi-acquirer). KTPay two-stage discovery + dev process (Jan 8).

How many packages need to be live at go-live vs added later?

high

Web research (Feb 2026): ~193 FIT packages total (VBR ~130, GRJ ~63). Recommend 30-50 top sellers at go-live, full catalog phased in 3-6 months post go-live. REQUIRES CONFIRMATION — actual active SKU count may differ from website listings.

What is the GP Solutions commercial model? (connection fee + monthly fee structure)

medium

Tracy working on getting pricing. Affects total cost picture for Vitruvian.

Can Jonview activities/excursions be included in MVP scope (not just accommodation)?

medium

Ragnar to confirm. Jonview API may be accommodation-only through GP Solutions. Kaptio provides service code mapping tooling.

What is the Sage export format needed? Can Kaptio reports be formatted to match Sage flat files?

medium

Finance deep dive (Jan 29). Tomas agreed it is theoretically possible with development work.

Is GRJ willing to co-invest on rail integration acceleration?

medium

Rail is core to their business. Co-investment could pull rail integration forward. Distribution (MGB aggregator) is 2027 prospect.

Who exactly from GRJ will participate in discovery workshops and UAT?

medium

Feb 12 confirmed Kaptio does heavy lifting. Kerry (CIO), Julian (ops), Missy (US) identified. No dedicated PM confirmed. Need names + availability.

Confirm full team size (UK + US) and roles beyond 7 US agents?

low

Web research: ~223 employees total group. ~35+ at York HQ. REQUIRES CONFIRMATION — only 7 US agents directly confirmed.

Confirm US booking season mirrors UK Boxing Day - mid-Feb peak?

low

Tracy confirmed UK peak booking is Boxing Day through mid-Feb (Feb 12). Assumes US follows suit. REQUIRES CONFIRMATION.